AssetWise CONNECT Edition Implementation Guide

To Define Program Priorities

In order to set up Programs for use in AssetWise CONNECT Edition ALIM, you must define the Program attributes for relevant Asset classes. One of the attributes is Program Priorities. Each line item in a Program requires a priority ranking. For more information about creating line items, see Creating Line Items.

Follow these steps to define Program Priorities.

  1. In AssetWise Director, navigate to System Admin, then select Maintain List Values.
  2. Expand Priorities in the tree.
  3. Select Program.
  4. In the List Values area, create each of the possible values to appear in the list. For example, create a list item and enter its Description, for example, "Low", and then assign a corresponding Priority value, for example,"1".
  5. Repeat step 3 for each Program Priority list item.
For example,